An exterior repaint is mostly preparation. The color goes on quickly at the end, but the days before it decide whether the paint is still tight to the siding after a few Clarksville summers. Here is the order we run a typical house in, one working day at a time.

How We Handle a Full Exterior Repaint, Day by Day

Clarksville, Tennessee
SJ & J Quality Paint & Remodel LLC painting and remodeling in Clarksville

Before day one: the walk-around and the written scope

We walk every side of the house with you before anything goes on the calendar. We press on trim boards at the corners and under windows, look for paint peeling down to bare wood, and note where gutters drip onto the siding. All of that goes into a written scope listing each surface, the prep it needs and the order it gets done in, so nobody is guessing when the crew pulls up.

We also photograph every elevation before we touch it. Those pictures become the baseline we compare against at each stage, and you get copies.

Day 1: washing, then waiting

The first real day is water. We wash the siding, trim and soffits to strip off chalky old paint, pollen, mildew and the green film that grows on the shady side of so many houses here. Paint laid over that film lets go early, however good the can was.

Then the house has to dry. In a humid stretch that can take the rest of the day and part of the next, and we would rather lose a morning than trap moisture under a fresh coat. Shrubs get tied back or covered, and anything stacked along the foundation is moved away from the walls.

Day 2: scraping, sanding and repairs

Loose paint is scraped back to a sound edge, and the ridges are sanded so they do not show through the finish. Soft trim, split window sills and rotted corner boards are cut out and replaced with new stock before primer goes anywhere near them. Cracked or damaged siding panels get patched or swapped at this stage too.

This is usually the messiest day. Chips land on drop cloths instead of the lawn, and the cloths are shaken out and the beds raked before the crew leaves.

Day 3: caulk and primer

Every gap where trim meets siding, every window and door casing, and every nail hole that has opened up gets fresh caulk. Old, cracked caulk is cut out first rather than buried under new. Bare wood and every repaired section get a primer suited to that surface, so the topcoat has something to grip.

Days 4 and 5: body color, trim and doors

The main walls go on first, usually in two coats, and we follow the shade around the house so the paint is not baking in direct afternoon sun while it sets. Trim, fascia and window casings come next, then doors and shutters last, since they get handled the most. On brick ranches, where only the trim, eaves and garage door take paint, this stretch moves faster.

If rain moves into the forecast, we shift the order rather than push through. Fresh paint needs several dry hours before weather reaches it.

Last day: punch list and clean-up

We walk the house with you again, scope in hand, and mark anything that needs a touch-up with a strip of tape. Those spots get fixed before we pack up. The final photos sit beside the first set so you can compare each side.

Then the site gets cleared: drop cloths up, ladders down, and a magnet sweep across the driveway and flower beds for any stray nails left from the trim repairs. Labeled leftover paint stays with you for future touch-ups.